Line 15: | Line 15: |
Back-up release managers are the two RMs from the previous two cycles. One option that has worked very well is to share the release-manager role across timezones, handing over the current status and tasks to the backup in the next timezone at the end of your day. It's a great opportunity to work together as a team. |
|
Line 18: | Line 22: |
* OOPS report * Merge proposal |
* OOPS reports * Merge proposals * [[https://wiki.canonical.com/InformationInfrastructure/OSA/LaunchpadProductionStatus|LaunchpadProductionStatus]] (private) |
Line 23: | Line 28: |
=== Before the roll-out === | === Week 3 (the one before the roll-out) === * During week 3 ensure that staging is [[https://staging.launchpad.net/successful-updates.txt|up-to-date]] so that it can be used for non-edge QA. * During week 3 ensure that Matt Revell has a downtime announcement email ready for lp-announce. * The down-time estimate should be based on the last staging DB restore. * During week 3 send out an email to Stuart Metcalf from Canonical ISD about the upcoming roll-out to ask about any changes that need to be rolled-out for canonical-identity-provider or shipit. (Launchpad roll-outs imply a roll-out of the Canonical Identity Provider and ShipIt code). * You might want to request that pqm-blockers (such as cherry-picks) are not processed on the day that PQM is closing. * At the end of the week, make sure all the cowboys listed on [[https://wiki.canonical.com/InformationInfrastructure/OSA/LaunchpadProductionStatus|LaunchpadProductionStatus]] are either already landed or listed among CurrentRolloutBlockers * Also go through all the 'unusual rollout requirements' and clean them up from [[https://wiki.canonical.com/InformationInfrastructure/OSA/LaunchpadProductionStatus|LaunchpadProductionStatus]] page === Release Week === |
Line 26: | Line 50: |
in PQM. * Update the `#launchpad-dev` topic to list him as release-manager. |
in PQM. (Monday 00:00 UTC) * There is an option to leave devel open for r-c landings as well until Tuesday. * At the beginning of week 4, schedule a call with the Foundations team lead (and other leads if known to be pertinent) to determine what system changes might need comprehensive QA. If these exist, consider these thoughts. * Any related problem encountered should be treated as a red flag, forcing more thorough QA. * Foundations lead should report on reviewing logs on edge, such as of cronscript output. * Look at the staging DB restore time for the week-end and determine if any changes to the announced down-time should be made. * Determine the schedule and deadlines. Send an email to launchpad-dev with all of the deadlines, similar to this [[ExampleReleaseScheduleEmail|example email]]. Place the deadlines on the team calendar. * Update the `#launchpad-dev` topic to state we are in 'Release Critical' and to list the release manager. |
Line 33: | Line 74: |
continuously to ensure that the list of release blockers is up to date. All bugs that are likely to cause lots of OOPSes, time outs or prevent |
continuously to ensure that the list of release blockers is up-to-date. (We need to explore a work-around to retire this wiki page and do the management in Launchpad.) All bugs that are likely to cause lots of OOPSes, time-outs or prevent |
Line 38: | Line 80: |
It's a good idea to subscribe yourself to the page. (Currently broken.) |
|
Line 40: | Line 84: |
* Review release-critical merge. | * Review release-critical merge proposals. The policy should be: * All RC candidates go through the normal review process. * After code and UI review the MP is left in 'Needs Review' state. * A new review of type 'release-critical' is added to the MP and assigned to the release manager. * If the MP is approved for 'release-critical', the review is marked 'Approve' and the state of the MP is set to 'Approved'. |
Line 45: | Line 93: |
* Request that landing to the `devel` branch be closed. (All changes should on the last day be merged through `db-devel`.) |
* Check that the LOSA do a staged deployment of the code. We are looking for any hidden build problems and to determine the amount of time this step will take. * Request that landing to the `devel` branch be closed, 24 hours before the scheduled release. All changes should on the last day be merged through `db-devel`. |
Line 54: | Line 104: |
* Remind people that all changes need to be in buildbot for '''6 hours''' before the roll-out time. |
* With PQM remaining open, have the LOSAs stop buildbot and set it do manual runs. * Remind people that all changes need to be in buildbot for '''9 hours''' before the roll-out time. The LOSAs require two hours of pre-release preparation and we need to allow for two complete buildbot cycles. (9 = 2 + 2 * 3.5) |
Line 61: | Line 113: |
* Ensure that any embargoed external resources (e.g. blog entries) are live and accessible through the links provided. Ensure that a blog editor (Matthew Revell or delegate) is available at the time of the roll-out. * Immediately after the roll-out, examine the site for problems. For example, ensure CSS loads properly, all external links on the front page are reachable, etc. * Check that source code dependencies revision numbers are correct (compare them with what is listed in `utilities/sourcedeps.conf`) "bzr branch lp:~launchpad-pqm/lp-production-configs/trunk" then look at config-manager/production-{devel,stable} === During the roll-out === * If some unexpected problems are encountered during the roll-out and these put the roll-out schedule off-track by more than 30 minutes, the decision to abort the roll-out should be taken. In that case: * Identify the source of the problem and come up with a best estimate on how soon it can be fixed. * Determine when the next attempt should be undertaken and make sure it is announced. Give at least 12 hours of fore-notice. |
|
Line 66: | Line 136: |
All common OOPSes are canditates for more release-critical fixes and | All common OOPSes are candidates for more release-critical fixes and |
Line 69: | Line 139: |
Line 75: | Line 146: |
* The release-manager need to select the next release manager. | * The release-manager needs to select the next release manager. == Re-opening PQM == Once the roll out is complete and any critical issues have been dealt with, it's time to re-open PQM. Before doing that, though, we need to merge db-devel back into devel. |
Line 80: | Line 155: |
merge proposal on Launchpad. The release manager simply add a review of type `release-critical` to the merge proposal. * Any issues found during QA that is bound to create OOPSes, time outs or be very inconveniencing to users are good candidate for release-critical approval. * Apart special exceptions discussed with the project lead, only bug fixes |
merge proposal on Launchpad. The engineer adds a review of type `release-critical` to the merge proposal and ensures it is in the 'Needs Review' state. * Good candidates for release-critical approval are issues found during QA that are bound to create OOPSes and time outs or otherwise significantly inconvenience our end-users. * Apart from special exceptions discussed with the project lead, only bug fixes |
Line 90: | Line 164: |
* If there is no way that the developer can QA his change on staging through the normal update procedure before the roll-out, for complex changes, it's recommended to ask a cow-boy of the branch on staging to QA it before approval. * For the second roll-out, any change requiring database changes should go through the project lead, since a re-roll with a DB updates creates significant down-time for our users. |
* If there is no way for the developer to QA his change on staging through the normal update procedure before the roll-out, it's recommended to request a cowboy of the branch on staging to QA it before approval. === Database Patches === * Release-critical branches containing database patches should only be accepted if they don't impact the estimated roll-out time. * One the day of the roll-out, only database patches that would be critical to prevent data corruption should be accepted. * For the second re-roll, again only DB patches critical to data safety should be considered as it impacts our ability to update without down-time. |
Line 102: | Line 181: |
* Engineer apply in advance for one cycle. * They are selected by the previous release manager. Once selected, their |
* Engineers apply in advance for one cycle. * They are selected by the previous release manager. Once selected, their name |
Line 107: | Line 186: |
* The actual roll-out time is determined based on the release-manager location: |
* The actual roll-out time is determined by the release-manager's location: |
Line 111: | Line 189: |
|| Americas || 00:00UTC || || Europe || 09:00UTC || |
|| Americas || 23:00UTC || || Europe || 10:00UTC || |
Line 115: | Line 193: |
* No engineer can apply for the role more than twice a year. | * No engineer should apply for the role more than twice a year. == References == * [[https://wiki.canonical.com/InformationInfrastructure/OSA/LaunchpadRollout | OSA Launchpad Rollout Procedures]] * SpuriousFailures -- useful for diagnosing last-minute build failures * CurrentRolloutBlockers -- things currently blocking rollout * [[QATeam/TestPlans]] -- proof from all the teams that their code works * [[https://wiki.canonical.com/InformationInfrastructure/OSA/LaunchpadProductionStatus|Launchpad production status]] |
Process Name: Release Manager Rotation Process
Process Owner: Francis Lacoste
Parent Process/Activity: None
Supported Policy: None
Process Overview
Each cycle a different engineer takes the role of release manager. The release manager coordinates with the release team and all team leads to ensure that the tree is ready for the roll-out and that all critical bugs are in or worked-around.
Back-up release managers are the two RMs from the previous two cycles.
One option that has worked very well is to share the release-manager role across timezones, handing over the current status and tasks to the backup in the next timezone at the end of your day. It's a great opportunity to work together as a team.
Release Manager inputs
- Email and IRC messages from engineers and team leads.
- OOPS reports
- Merge proposals
LaunchpadProductionStatus (private)
Activities
Week 3 (the one before the roll-out)
During week 3 ensure that staging is up-to-date so that it can be used for non-edge QA.
- During week 3 ensure that Matt Revell has a downtime announcement email ready for lp-announce.
- The down-time estimate should be based on the last staging DB restore.
- During week 3 send out an email to Stuart Metcalf from Canonical ISD about the upcoming roll-out to ask about any changes that need to be rolled-out for canonical-identity-provider or shipit. (Launchpad roll-outs imply
a roll-out of the Canonical Identity Provider and ShipIt code).
- You might want to request that pqm-blockers (such as cherry-picks) are not processed on the day that PQM is closing.
At the end of the week, make sure all the cowboys listed on LaunchpadProductionStatus are either already landed or listed among CurrentRolloutBlockers
Also go through all the 'unusual rollout requirements' and clean them up from LaunchpadProductionStatus page
Release Week
- At the beginning of week 4. Make sure that release-critical was turned on in PQM. (Monday 00:00 UTC)
- There is an option to leave devel open for r-c landings as well until Tuesday.
- At the beginning of week 4, schedule a call with the Foundations team lead (and other leads if known to be pertinent) to determine what system changes might need comprehensive QA. If these exist, consider these thoughts.
- Any related problem encountered should be treated as a red flag, forcing more thorough QA.
- Foundations lead should report on reviewing logs on edge, such as of cronscript output.
- Look at the staging DB restore time for the week-end and determine if any changes to the announced down-time should be made.
Determine the schedule and deadlines. Send an email to launchpad-dev with all of the deadlines, similar to this example email. Place the deadlines on the team calendar.
Update the #launchpad-dev topic to state we are in 'Release Critical' and to list the release manager.
Maintain the list of the Current roll-out blockers
- The release manager should poll the team leads and QA engineers continuously to ensure that the list of release blockers is up-to-date. (We need to explore a work-around to retire this wiki page and do the management in Launchpad.) All bugs that are likely to cause lots of OOPSes, time-outs or prevent several users from working are good CRB candidates. It's a good idea to subscribe yourself to the page. (Currently broken.)
- Make sure that developers are assigned to all problems we want to fix.
- Review release-critical merge proposals. The policy should be:
- All RC candidates go through the normal review process.
- After code and UI review the MP is left in 'Needs Review' state.
- A new review of type 'release-critical' is added to the MP and assigned to the release manager.
- If the MP is approved for 'release-critical', the review is marked 'Approve' and the state of the MP is set to 'Approved'.
On the day before the roll-out
- Check that the LOSA do a staged deployment of the code. We are looking for any hidden build problems and to determine the amount of time this step will take.
Request that landing to the devel branch be closed, 24 hours before the scheduled release. All changes should on the last day be merged through db-devel.
On the day of the roll-out
Chase up Current Rollout Blockers and any other pending release-critical fixes.
- With PQM remaining open, have the LOSAs stop buildbot and set it do manual runs.
Remind people that all changes need to be in buildbot for 9 hours before the roll-out time. The LOSAs require two hours of pre-release preparation and we need to allow for two complete buildbot cycles. (9 = 2 + 2 * 3.5)
- In the case of failures, it's best to roll-out the last-known-good-build rather than delaying the release. The cut-off point to decide which revision
to roll out is 2 hours before the scheduled release.
- Ensure that any embargoed external resources (e.g. blog entries) are live and accessible through the links provided. Ensure that a blog editor (Matthew Revell or delegate) is available at the time of the roll-out.
- Immediately after the roll-out, examine the site for problems. For example, ensure CSS loads properly, all external links on the front page are reachable, etc.
- Check that source code dependencies revision numbers are correct (compare
them with what is listed in utilities/sourcedeps.conf) "bzr branch lp:~launchpad-pqm/lp-production-configs/trunk" then look at config-manager/production-{devel,stable}
During the roll-out
- If some unexpected problems are encountered during the roll-out and these put the roll-out schedule off-track by more than 30 minutes, the decision to abort the roll-out should be taken. In that case:
- Identify the source of the problem and come up with a best estimate on how soon it can be fixed.
- Determine when the next attempt should be undertaken and make sure it is announced. Give at least 12 hours of fore-notice.
After the roll-out
- With the QA engineers, review the OOPS reports.
- All common OOPSes are candidates for more release-critical fixes and scheduling another roll-out.
- Prepare and schedule any necessary re-roll.
- When a re-roll is needed, same activities than in the pre-roll out case.
- Open the tree, when the released version is fine for the next cycle.
- The release-manager needs to select the next release manager.
Re-opening PQM
Once the roll out is complete and any critical issues have been dealt with, it's time to re-open PQM. Before doing that, though, we need to merge db-devel back into devel.
Release critical policy
- To apply for a release-critical approval, you must have a reviewed merge proposal on Launchpad. The engineer adds a review of type
release-critical to the merge proposal and ensures it is in the 'Needs Review' state.
- Good candidates for release-critical approval are issues found during QA that are bound to create OOPSes and time outs or otherwise significantly inconvenience our end-users.
- Apart from special exceptions discussed with the project lead, only bug fixes should be granted release-critical approval.
- If there is no way for the developer to QA his change on staging through the normal update procedure before the roll-out, it's recommended to request a cowboy of the branch on staging to QA it before approval.
Database Patches
- Release-critical branches containing database patches should only be accepted if they don't impact the estimated roll-out time.
- One the day of the roll-out, only database patches that would be critical to prevent data corruption should be accepted.
- For the second re-roll, again only DB patches critical to data safety should be considered as it impacts our ability to update without down-time.
Scheduling
- Engineers apply in advance for one cycle.
- They are selected by the previous release manager. Once selected, their name
is put on the Launchpad Production Status page.
- The actual roll-out time is determined by the release-manager's location:
Location
Roll out time
Americas
23:00UTC
Europe
10:00UTC
Asia/Pacific
00:00UTC
- No engineer should apply for the role more than twice a year.
References
SpuriousFailures -- useful for diagnosing last-minute build failures
CurrentRolloutBlockers -- things currently blocking rollout
QATeam/TestPlans -- proof from all the teams that their code works