Line 1: Line 1:
## page was renamed from PolicyAndProcess/ReleaseManagerRotation
Line 3: Line 4:
 * '''Process Name:''' Release Manager Rotation Process  * '''Process Name:''' Monthly DB deployment with downtime
Line 10: Line 11:
Each cycle a different engineer takes the role of release manager. The release
manager coordinates with the release team and all team leads to ensure that
the tree is ready for the roll-out and that all critical bugs are in or
worked-around.
Each month a DB downtime is scheduled. The team lead schedules this with the Launchpad stakeholders and LOSAs. It is broadly scheduled up to a year in advance on [[DowntimeDeploymentSchedule|the downtime schedule]]. The scheduled time should overlap with availability from the DBA
Line 15: Line 13:
Back-up release managers are the two RMs from the previous two cycles. The launchpad engineers request a merge from db-stable of *only* QA-ok commits 48 hours before the scheduled time. The db downtime then deploys just that merge revision and where possibly only does schema changes.
Line 17: Line 15:
One option that has worked very well is to share the release-manager role across timezones, handing over the current status and tasks to the backup in the next timezone at the end of your day. It's a great opportunity to work together as a team. Other downtime requiring events (such as codehosting setup changes) have partial downtime scheduled as required.
Line 19: Line 17:
== Release Manager inputs == == DB-stable->devel merge imputs ==
Line 22: Line 20:
  * OOPS reports
  * Merge proposals
  * [[https://wiki.canonical.com/InformationInfrastructure/OSA/LaunchpadProductionStatus|LaunchpadProductionStatus]] (private)
  * Deployment reports
   * [[https://devpad.canonical.com/~lpqateam/qa_reports/deployment-stable.html|stable]]
   * [[https://devpad.canonical.com/~lpqateam/qa_reports/deployment-db-stable.html|db-stable]]
Line 28: Line 26:
=== When you start === === Coordinator (LP Team lead) ===
Line 30: Line 28:
 * Negotiate and confirm the dates and times for the main release window and a backup release window with the Launchpad Project Lead, then with the LOSAs and OEM, and finally with the stakeholder's list (Platform, etc.).  Refer to the [[Releases/2010Calendar|Launchpad Release Calendar]] for the pre-scheduled dates and times (we has a process in place to ensure our release calendar does not conflict with Ubuntu; conflicts normally do not happen). The goal is to confirm that the scheduled downtime does not interrupt other teams at critical times, to ensure that the release window does not place undue stress or risk upon our own operations team, and renegotiate the dates and times if necessary.  * Negotiate and confirm the dates and times for the main release window and a backup release window with the following groups. Refer to the [[DowntimeDeploymentSchedule|the downtime schedule]] for the pre-scheduled dates and times (we have a process in place to ensure our release calendar does not conflict with Ubuntu; conflicts normally do not happen). The goal is to confirm that the scheduled downtime does not interrupt other teams at critical times, to ensure that the release window does not place undue stress or risk upon our own operations team, and renegotiate the dates and times if necessary. Note when scheduling that services on Launchpad can begin being paused up to half an hour before the rollout.
Line 32: Line 30:
  * Check the stakeholders list archives for the mails I sent out if you are looking for a template. -- [[LaunchpadHome:mars]] <<DateTime(2010-07-29T14:37:13Z)>>    * the stakeholder's list (private-canonical-launchpad-stakeholders@lists.launchpad.net).
   * the LOSAs (losas@canonical.com)
   * the DBA (Stuart Bishop <stuart.bishop@canonical.com>)
Line 34: Line 34:
  * Consider when critical people have scheduled holidays and vacation around the release date. You can run a release without critical people like DB reviewers or the Project Lead, but it increases the stress and risk when something goes wrong. -- [[LaunchpadHome:mars]] <<DateTime(2010-07-29T14:37:13Z)>> Let Matthew Revell <matthew.revell@canonical.com> know the time to announce it.
Line 36: Line 36:
  * We consider the backup release window now because getting feedback from all the stakeholders can take a few days. Presumably you want to try a second rollout as soon as possible after the first (ask the LOSAs about what a reasonable backup window would be). -- [[LaunchpadHome:mars]] <<DateTime(2010-07-29T14:52:37Z)>> The downtime window is always 90 minutes; if less time is consumed, great. If more time is needed, we go back to the drawing board to figure out how to do it faster.
Line 38: Line 38:
 * Ask Stuart M. on the ISD team if they need to roll out an update to ShipIt with this release. ShipIt releases are bundled with Launchpad releases. Re-announce downtime so it serves as a reminder on [[http://identi.ca/launchpadstatus|launchpadstatus]] account at '''least 4h''' before the actual rollout. You can do this yourself with the [[https://wiki.canonical.com/Launchpad/PolicyandProcess/Announcements/Downtime|identi.ca login info]].
Line 40: Line 40:
Ensure that Matt Revell has a downtime announcement email ready for lp-announce. Again, make sure it's noted that some LP services (e.g. soyuz) can go offline temporarily up to half an hour before the rollout.
Line 41: Line 42:
=== End of Week 2 === === Engineering responsibilities ===
Line 43: Line 44:
  .☐ Notify the canonical-launchpad list of the expected date and time for PQM closure. This should ideally happen at least 1 week before PQM closes; at the latest it should happen at the start of Week 3.  * All QA for db changes must include checking that the aggregate database time is within budget. To find out how long the database updates will take to deploy on production, double the aggregate time from staging and add 10 minutes. Grep for lines like "2208-30-0 applied just now in 70.5 seconds"in devpad:/x/launchpad.net-logs/staging/sourcherry/2011-*-staging_restore.log
 * If the aggregate time is too large, either merge less than all the possible revisions, or back out the problem revision. This is part of qaing on db-stable.
Line 45: Line 47:
 * Ask losas to merge db-stable rev XXX to `devel` and put PQM into RC mode. ('on prae as pqm {{{cd /home/pqm/archives/rocketfuel/launchpad/devel; bzr update; bzr revert; bzr merge -r 10381 lp:~launchpad-pqm/launchpad/db-stable; bzr commit -m "Merge db-stable 10381." ; bzr push lp:~launchpad-pqm/launchpad/devel}}}. If there are conflicts a developer should reproduce the merge and tell the LOSA how to resolve them.
 * After buildbot blesses the merge ask LOSA to do the upgrade to qastaging ('refresh the qastaging tree on sourcherry, run normal upgrade scripts there')
 * '''While in RC mode:'''
    * Anyone can land 'release-critical' branches on `devel` that contain
    changes that would prevent the deployment from succeeding. This include
    fix or reversal for items marked `qa-bad`. Use `[release-critical=<you>]` in the PQM commit message.
    * A good rule of thumb to apply is: Does landing this change will save us from handling [[https://wiki.canonical.com/Launchpad/PolicyandProcess/CrisisHandlingPolicy|an incident]] during or shortly after the deployment? In the affirmative, land it!
    * For all other changes (features that would be delayed, nice to have fixes, annoyances to user, etc.) approval is required from either the [[https://launchpad.net/~launchpad-leader|project lead]], [[https://launchpad.net/~launchpad-architect|technical architect]] or [[https://launchpad.net/~launchpad-strategist|product strategist]].
 * Ask losas to take PQM out of RC mode once verifying that qastaging is working well (e.g. re-qa all the schema changes included in the merge).
  * Update the `#launchpad-dev` topic to state 'PQM in RC mode' and then reverse it.
Line 46: Line 58:
=== Week 3 (the one before the roll-out) ===   * Make sure all the cowboys listed on [[https://wiki.canonical.com/InformationInfrastructure/OSA/LaunchpadProductionStatus|LaunchpadProductionStatus]] are either already landed or are added to the 'unusual rollout requirements' on that same page, so that the LOSAs will re-apply the cowboys after the rollout. It is definitely preferable not to re-apply cowboys, so it's a good idea to track down who hasn't landed a permanent fix yet.
Line 48: Line 60:
Preparation is required. Many items can be considered critical.   * If some unexpected problems are encountered during the roll-out and these put the roll-out schedule off-track by more than 30 minutes, and it can be aborted, then it should be aborted. In that case:
Line 50: Line 62:
==== Start of Week 3 ====   * Identify the source of the problem and come up with a best estimate on how soon it can be fixed.
Line 52: Line 64:
  .☐ Ensure that staging is [[https://staging.launchpad.net/successful-updates.txt|up-to-date]] and had a [[https://lpstats.canonical.com/graphs/StagingRestoreDurations/ | DB restore]] so that it can be used for non-edge QA.

  .☐ The down-time estimate should be based on the last staging DB restore. We should be overly conservative in the read-only announcement. Recently, we always encountered DB locking issues during the roll-out which increased the read-only window. Until we are able to have stable DB upgrades and determine a reliable fudge factor between time on staging and production, we should plan for the worst and come back earlier.

  .☐ Follow [[https://bugs.edge.launchpad.net/launchpad-project/+bugs?field.tag=qa-needstesting | the needs testing bugs]] and encourage engineers to QA before PQM closes.


==== During Week 3 ====

  .☐ Ensure that Matt Revell has a downtime announcement email ready for lp-announce.

  .☐ Send out an email to Stuart Metcalf from Canonical ISD about the upcoming roll-out to ask about any changes that need to be rolled-out for canonical-identity-provider or shipit. (Launchpad roll-outs imply a roll-out of the Canonical Identity Provider and ShipIt code).


==== End of Week 3 ====

On the day the PQM closes.

  .☐ Also go through all the 'unusual rollout requirements' and clean them up from [[https://wiki.canonical.com/InformationInfrastructure/OSA/LaunchpadProductionStatus|LaunchpadProductionStatus]] page

  .☐ You might want to request that pqm-blockers (such as cherry-picks) are not processed on the day that PQM is closing.

  .☐ Make sure all the cowboys listed on [[https://wiki.canonical.com/InformationInfrastructure/OSA/LaunchpadProductionStatus|LaunchpadProductionStatus]] are either already landed or listed among CurrentRolloutBlockers

  .☐ Offer to review anything '''may''' need a release critical. Provide your RC to any work that may miss the PQM close time (EC2 is unpredictable). Providing RCs '''before''' the close of PQM allows engineers to work with some certainty that there work is required.

  .☐ Ask Matthew to update db-devel with the Recent Launchpad blog posts.

  .☐ Ask the LOSAs to switch PQM to release-critical around 22:00 UTC (Friday or Thursday). Allow landing to devel.

  .☐ Update the `#launchpad-dev` topic to state we are in 'Release Critical' and to list the release manager.

  .☐ Be prepared to make test fixes over the weekend to ensure the last branches are complete, or back them out so that staging is ready for testing Monday


=== Release Week ===

==== Start of Week 4 ====

  .☐ At the beginning of week 4, schedule a call with the Foundations team lead (and other leads if known to be pertinent) to determine what system changes might need comprehensive QA. If these exist, consider these thoughts.

     * Any related problem encountered should be treated as a red flag,
     forcing more thorough QA.

     * Foundations lead should report on reviewing logs on edge, such
     as of cronscript output.

  .☐ Look at the staging DB restore time for the week-end and determine if any changes to the announced down-time should be made.

  .☐ Determine the schedule and deadlines. Send an email to launchpad-dev with all of the deadlines, similar to this [[ExampleReleaseScheduleEmail|example email]]. Place the deadlines on the team calendar.

  .☐ Maintain the list of the [[CurrentRolloutBlockers|Current roll-out blockers]]


==== During Week 4 ====

  .☐ The release manager should poll the team leads and QA engineers continuously to ensure that the list of release blockers is up-to-date. (We need to explore a work-around to retire this wiki page and do the management in Launchpad.)

      * All bugs that are likely to cause lots of OOPSes, time-outs or prevent
      several users from working are good CRB candidates.

      * It's a good idea to subscribe yourself to the page. (Currently broken.)

  .☐ Make sure that developers are assigned to all problems we want to fix.

  .☐ Review release-critical merge proposals. The policy should be:

     * All RC candidates go through the normal review process.
     * After code and UI review the MP is left in 'Needs Review' state.
     * A new review of type 'release-critical' is added to the MP and assigned
     to the release manager.
     * If the MP is approved for 'release-critical', the review is marked
     'Approve' and the state of the MP is set to 'Approved'.

  .☐ Consider closing devel for RC landings (Tuesday is usually the latest devel can be open)


==== On the day before the roll-out ====

  .☐ Ensure that PQM is closed to devel, RC landing go to db-devel.

  .☐ Check that the LOSA do a staged deployment of the code. We are looking for any hidden build problems and to determine the amount of time this step will take.

  .☐ Ensure that any embargoed external resources (e.g. blog entries) are live and accessible through the links provided. Ensure that a blog editor (Matthew Revell or delegate) is available at the time of the roll-out.


==== On the day of the roll-out ====

  .☐ Chase up ''Current Rollout Blockers'' and any other pending release-critical fixes.

  .☐ With PQM remaining open, have the LOSAs stop buildbot and set it do manual runs. This step just keeps the buildmaster process tree tidy when the codehost servers are restarted.

  .☐ Remind people that all changes need to be in buildbot for '''9 hours''' before the roll-out time. The LOSAs require two hours of pre-release preparation and we need to allow for two complete buildbot cycles. (9 = 2 + 2 * 3.5)

  .☐ In the case of failures, it's best to roll-out the last-known-good-build rather than delaying the release. The cut-off point to decide which revision to roll out is '''2 hours''' before the scheduled release.

  .☐ Re-announce downtime so it serves as a reminder on [[http://identi.ca/launchpadstatus|launchpadstatus]] account at '''least 4h''' before the actual rollout.

  .☐ Check that source code dependencies revision numbers are correct (compare them with what is listed in `utilities/sourcedeps.conf`) "bzr branch lp:~launchpad-pqm/lp-production-configs/trunk" then look at config-manager/production-{devel,stable}

   * '''This step appears to be obsolete - the lp-production-configs have not changed for six months! -- [[LaunchpadHome:mars]] <<DateTime(2010-07-06T21:51:47Z)>>'''

  .☐ Start a new [[https://wiki.canonical.com/Launchpad/RolloutReports|RolloutReport]] to document any issues that will be encountered during the roll-out.


==== During the roll-out ====

  .☐ If some unexpected problems are encountered during the roll-out and these put the roll-out schedule off-track by more than 30 minutes, the decision to abort the roll-out should be taken. In that case:

  .☐ Identify the source of the problem and come up with a best estimate on how soon it can be fixed.

  .☐ Determine when the next attempt should be undertaken and make sure it is announced. Give at least 12 hours of fore-notice.
  * Determine when the next attempt should be undertaken (usually: the backup window) and make sure it is announced. Give at least 24 hours of advance warning (because the readonly replica takes 24 hours to restore).
Line 168: Line 68:
  .☐ Immediately after the roll-out, examine the site for problems. For example, ensure CSS loads properly, all external links on the front page are reachable, etc.   * Immediately after the roll-out, examine the site for problems. For example, ensure CSS loads properly, all external links on the front page are reachable, etc.
Line 170: Line 70:
  .☐ Announce on `launchpadstatus` that the release is done.   * Announce on `launchpadstatus` that the release is done.
Line 172: Line 72:
  .☐ Announce any post-roll out issues on `lauchpadstatus` as they are discovered. Add them to the incident report. (Following the Launchpad/PolicyandProcess/Announcements/IncidentProcess, where the release manager acts as the communication liaison.)

  .☐ With the QA engineers, review the OOPS reports. All common OOPSes are candidates for more release-critical fixes and scheduling another roll-out.

  .☐ Prepare and schedule any necessary re-roll.

  .☐ When a re-roll is needed, same activities than in the pre-roll out case.

  .☐ Complete the incident report and ask any engineers that participated in fixing the issues in doing root-cause analysis.

  .☐ The release-manager needs to select the next release manager.


== Re-opening PQM ==

Once the roll out is complete and any critical issues have been dealt with,
it's time to re-open PQM. Before doing that, though, we need to merge db-devel
back into devel.

== Release critical policy ==

  * To apply for a release-critical approval, you must have a reviewed
  merge proposal on Launchpad. The engineer adds a review of type
  `release-critical` to the merge proposal and ensures it is in the 'Needs Review' state.

  * Good candidates for release-critical approval are issues found during QA that are
  bound to create OOPSes and time outs or otherwise significantly inconvenience our end-users.

  * Apart from special exceptions discussed with the project lead, only bug fixes
  should be granted release-critical approval.

  * If there is no way for the developer to QA his change on staging through
  the normal update procedure before the roll-out, it's recommended to request
  a cowboy of the branch on staging to QA it before approval.
  * Announce any post-roll out issues on `lauchpadstatus` as they are discovered. Create incident reports for them. (Following the Launchpad/PolicyandProcess/Announcements/IncidentProcess).
Line 209: Line 76:
  * Release-critical branches containing database patches should only
  be accepted if they don't impact the estimated roll-out time.

  * One the day of the roll-out, only database patches that would be critical
  to prevent data corruption should be accepted.

  * For the second re-roll, again only DB patches critical to data safety
  should be considered as it impacts our ability to update without down-time.

== Scheduling ==

  * Engineers apply in advance for one cycle.

  * They are selected by the previous release manager. Once selected, their name
  is put on the [[https://wiki.canonical.com/InformationInfrastructure/OSA/LaunchpadProductionStatus|Launchpad Production Status page]].

  * The actual roll-out time is determined by the release-manager's location:

        || Location || Roll out time ||
        || Americas || 23:00UTC ||
        || Europe || 10:00UTC ||
        || Asia/Pacific || 00:00UTC ||

  * No engineer should apply for the role more than twice a year.
  * If the qa-ok of a patch merged to devel was faulty and a fix is needed, this shouldn't impact the downtime - if it will, the entire thing should just be backed out.
Line 238: Line 82:
 * CurrentRolloutBlockers -- things currently blocking rollout
 * [[QATeam/TestPlans]] -- proof from all the teams that their code works
Line 241: Line 83:
 * [[https://wiki.canonical.com/Launchpad/PolicyandProcess/ProductionChangeApprovalPolicy|Approval of production change]]
 * [[https://wiki.canonical.com/Launchpad/PolicyandProcess/EmergencyChange|Emergency change (aka cherry-picks)]]

  • Process Name: Monthly DB deployment with downtime

  • Process Owner: Francis Lacoste

  • Parent Process/Activity: None

  • Supported Policy: None

Process Overview

Each month a DB downtime is scheduled. The team lead schedules this with the Launchpad stakeholders and LOSAs. It is broadly scheduled up to a year in advance on the downtime schedule. The scheduled time should overlap with availability from the DBA

The launchpad engineers request a merge from db-stable of *only* QA-ok commits 48 hours before the scheduled time. The db downtime then deploys just that merge revision and where possibly only does schema changes.

Other downtime requiring events (such as codehosting setup changes) have partial downtime scheduled as required.

DB-stable->devel merge imputs

  • Email and IRC messages from engineers and team leads.
  • Deployment reports

Activities

Coordinator (LP Team lead)

  • Negotiate and confirm the dates and times for the main release window and a backup release window with the following groups. Refer to the the downtime schedule for the pre-scheduled dates and times (we have a process in place to ensure our release calendar does not conflict with Ubuntu; conflicts normally do not happen). The goal is to confirm that the scheduled downtime does not interrupt other teams at critical times, to ensure that the release window does not place undue stress or risk upon our own operations team, and renegotiate the dates and times if necessary. Note when scheduling that services on Launchpad can begin being paused up to half an hour before the rollout.

Let Matthew Revell <matthew.revell@canonical.com> know the time to announce it.

The downtime window is always 90 minutes; if less time is consumed, great. If more time is needed, we go back to the drawing board to figure out how to do it faster.

Re-announce downtime so it serves as a reminder on launchpadstatus account at least 4h before the actual rollout. You can do this yourself with the identi.ca login info.

Ensure that Matt Revell has a downtime announcement email ready for lp-announce. Again, make sure it's noted that some LP services (e.g. soyuz) can go offline temporarily up to half an hour before the rollout.

Engineering responsibilities

  • All QA for db changes must include checking that the aggregate database time is within budget. To find out how long the database updates will take to deploy on production, double the aggregate time from staging and add 10 minutes. Grep for lines like "2208-30-0 applied just now in 70.5 seconds"in devpad:/x/launchpad.net-logs/staging/sourcherry/2011-*-staging_restore.log
  • If the aggregate time is too large, either merge less than all the possible revisions, or back out the problem revision. This is part of qaing on db-stable.
  • Ask losas to merge db-stable rev XXX to devel and put PQM into RC mode. ('on prae as pqm cd /home/pqm/archives/rocketfuel/launchpad/devel; bzr update; bzr revert; bzr merge -r 10381 lp:~launchpad-pqm/launchpad/db-stable; bzr commit -m "Merge db-stable 10381." ; bzr push lp:~launchpad-pqm/launchpad/devel. If there are conflicts a developer should reproduce the merge and tell the LOSA how to resolve them.

  • After buildbot blesses the merge ask LOSA to do the upgrade to qastaging ('refresh the qastaging tree on sourcherry, run normal upgrade scripts there')
  • While in RC mode:

    • Anyone can land 'release-critical' branches on devel that contain changes that would prevent the deployment from succeeding. This include fix or reversal for items marked qa-bad. Use [release-critical=<you>] in the PQM commit message.

    • A good rule of thumb to apply is: Does landing this change will save us from handling an incident during or shortly after the deployment? In the affirmative, land it!

    • For all other changes (features that would be delayed, nice to have fixes, annoyances to user, etc.) approval is required from either the project lead, technical architect or product strategist.

  • Ask losas to take PQM out of RC mode once verifying that qastaging is working well (e.g. re-qa all the schema changes included in the merge).
    • Update the #launchpad-dev topic to state 'PQM in RC mode' and then reverse it.

    • Make sure all the cowboys listed on LaunchpadProductionStatus are either already landed or are added to the 'unusual rollout requirements' on that same page, so that the LOSAs will re-apply the cowboys after the rollout. It is definitely preferable not to re-apply cowboys, so it's a good idea to track down who hasn't landed a permanent fix yet.

    • If some unexpected problems are encountered during the roll-out and these put the roll-out schedule off-track by more than 30 minutes, and it can be aborted, then it should be aborted. In that case:
    • Identify the source of the problem and come up with a best estimate on how soon it can be fixed.
    • Determine when the next attempt should be undertaken (usually: the backup window) and make sure it is announced. Give at least 24 hours of advance warning (because the readonly replica takes 24 hours to restore).

After the roll-out

  • Immediately after the roll-out, examine the site for problems. For example, ensure CSS loads properly, all external links on the front page are reachable, etc.
  • Announce on launchpadstatus that the release is done.

  • Announce any post-roll out issues on lauchpadstatus as they are discovered. Create incident reports for them. (Following the Launchpad/PolicyandProcess/Announcements/IncidentProcess).

Database Patches

  • If the qa-ok of a patch merged to devel was faulty and a fix is needed, this shouldn't impact the downtime - if it will, the entire thing should just be backed out.

References

PolicyAndProcess/Downtime (last edited 2011-06-06 22:02:02 by flacoste)