Deliverables
Whatever you need to keep track of deliverables. An example, including some common ones is included below. Deliverables often correspond to a group of user stories or a single user story
Item |
Owner |
Expected date |
Status |
Signed off LEPs |
lifeless |
2012-01-05 |
COMPLETED |
Secure test hardware |
flacoste |
2012-01-20 |
IN-PROGRESS |
Secure production hardware |
flacoste |
2012-02-22 |
|
Feature documentation |
gary |
|
|
Blog post |
gary |
|
|
Notes
Checkpoints Notes
Action items for next checkpoint
- [yellow] Reproduce existing parallel LXC setup
- [yellow] Close some of the existing bugs
- [flacoste] Requisition test hardware
- [yellow] Establish experimental plan to assess final hardware need.
- [yellow] Make prediction for success criteria