Parallel Testing

See also paralleltest bug tag

Squad started: 2012-01-02
Current week: 1
Next checkpoint: TBD

Scope

See the LEP

Out of scope

As documented in the LEP.

Blockers

None

Deliverables

Whatever you need to keep track of deliverables. An example, including some common ones is included below. Deliverables often correspond to a group of user stories or a single user story

Item

Owner

Expected date

Status

Signed off LEPs

lifeless

2012-01-05

COMPLETED

Secure test hardware

flacoste

2012-01-20

IN-PROGRESS

Secure production hardware

flacoste

2012-02-22

Feature documentation

gary

Blog post

gary

Notes

Checkpoints Notes

Action items for next checkpoint

  • [yellow] Reproduce existing parallel LXC setup
  • [yellow] Close some of the existing bugs
  • [flacoste] Requisition test hardware
  • [yellow] Establish experimental plan to assess final hardware need.
  • [yellow] Make prediction for success criteria