Parallel Testing
See also paralleltest bug tag
Squad started: 2012-01-02
Current week: 1
Next checkpoint: TBD
Scope
Out of scope
As documented in the LEP.
Blockers
None
Deliverables
Whatever you need to keep track of deliverables. An example, including some common ones is included below. Deliverables often correspond to a group of user stories or a single user story
Item |
Owner |
Expected date |
Status |
Signed off LEPs |
lifeless |
2012-01-05 |
COMPLETED |
Secure test hardware |
flacoste |
2012-01-20 |
IN-PROGRESS |
Secure production hardware |
flacoste |
2012-02-22 |
|
Feature documentation |
gary |
|
|
Blog post |
gary |
|
|
Notes
Checkpoints Notes
ACtion items for next checkpoint
- [yellow] Reproduce existing parallel LXC setup
- [yellow] Close some of the existing bugs
- [flacoste] Requisition test hardware
- [yellow] Establish experimental plan to assess final hardware need.
- [yellow] Make prediction for success criteria