Work Items
See also work-item-tracker bug tag
Started: 2012-01-30
Current week: 4
Next checkpoint: 2012-05-30 Blueprint:: https://blueprints.launchpad.net/linaro-infrastructure-misc/+spec/linaro-infra-misc-eng-views-pilot
Scope
Coming shortly.
Out of scope
- Reproduce status.*.* in Launchpad.
- API call to provide all work items for a project.
Deliverables
Item |
Owner |
Expected date |
Status |
Signed off LEPs |
mrevell |
2012-02-27 |
Drafting |
Work items text box in production |
salgado |
2012-03-07 |
DONE |
Team and individual work items view |
salgado, mattias |
2012-03-07 |
DONE |
Bugs and improvements |
danilo, james |
2012-05-31 |
INPROGRESS |
Feature documentation |
|
|
|
Blog post |
|
|
|
Actions for next checkpoint
- ACTION: [mrevell] Provide text for a help pop-up to go alongside the work items text box.
- ACTION: [linaro] Complete the UI for the work items text box and have it delete, add and update items as required.
- ACTION: [linaro] Have the migration script run on production and then contact, if necessary, the owners of any live blueprints whose work items weren't migrated.
- ACTION: [salgado] Send Huw his wireframes for the team and individual views.
- ACTION: [huwshimi] Review the mock-ups and give comments to Salgado.
- ACTION: [danhg] Test Salgado's revised wireframes.
- ACTION: [linaro] Implement a beta of the team and individual work item views.
Notes
Mock-ups