Line 6: Line 6:
'''Current week:''' 1<<BR>>
'''Next [[PolicyandProcess/FeatureDevelopmentCheckpoint|checkpoint]]:''' TBD
'''Current week:''' 6<<BR>>
'''Next [[PolicyandProcess/FeatureDevelopmentCheckpoint|checkpoint]]:''' 2012-02-22
Line 28: Line 28:
|| Get repeatable deployment story || yellow || 2012-02-22 || IN-PROGRESS ||
|| Determine scaling behavior || yellow || 2012-02-22 || ||
|| Root out instability || yellow || 2012-03-07 || ||
Line 38: Line 41:
 * [[12W9MbXPJ746x3I7YRbL2iBBPfjVJxWEGyOs3Quiwzr8|2012-01-05 kick-off call]]  * [[https://docs.google.com/document/d/12W9MbXPJ746x3I7YRbL2iBBPfjVJxWEGyOs3Quiwzr8/edit|2012-01-05 kick-off call]]
<<PageList(regex:^Projects/ParallelTesting/Checkpoint-*)>>
Line 40: Line 44:
== ACtion items for next checkpoint == == Action items for next checkpoint ==
Line 42: Line 46:
 * [yellow] Reproduce existing parallel LXC setup
 * [yellow] Close some of the existing bugs
 * [flacoste] Requisition test hardware
 * [yellow] Establish experimental plan to assess final hardware need.
 * [yellow] Make prediction for success criteria
 * [yellow] Charm done done (in official charm repo, demoable with LP)
 * [yellow] performance testing started with preliminary results

Parallel Testing

See also paralleltest bug tag

Squad started: 2012-01-02
Current week: 6
Next checkpoint: 2012-02-22

Scope

See the LEP

Out of scope

As documented in the LEP.

Blockers

None

Deliverables

Whatever you need to keep track of deliverables. An example, including some common ones is included below. Deliverables often correspond to a group of user stories or a single user story

Item

Owner

Expected date

Status

Signed off LEPs

lifeless

2012-01-05

COMPLETED

Secure test hardware

flacoste

2012-01-20

IN-PROGRESS

Get repeatable deployment story

yellow

2012-02-22

IN-PROGRESS

Determine scaling behavior

yellow

2012-02-22

Root out instability

yellow

2012-03-07

Secure production hardware

flacoste

2012-02-22

Feature documentation

gary

Blog post

gary

Notes

Checkpoints Notes

Action items for next checkpoint

  • [yellow] Charm done done (in official charm repo, demoable with LP)
  • [yellow] performance testing started with preliminary results

Projects/ParallelTesting (last edited 2012-04-12 00:47:39 by flacoste)