Size: 1728
Comment: Update based on Feb 22 checkpoint
|
Size: 1673
Comment: Bi-weekly checkpoints
|
Deletions are marked like this. | Additions are marked like this. |
Line 6: | Line 6: |
'''Current week:''' 6<<BR>> '''Next [[PolicyandProcess/FeatureDevelopmentCheckpoint|checkpoint]]:''' 2012-02-22 |
'''Current week:''' 8<<BR>> '''Next [[PolicyandProcess/FeatureDevelopmentCheckpoint|checkpoint]]:''' 2012-03-21 |
Line 27: | Line 27: |
|| Secure test hardware || flacoste || 2012-02-28 || IN-PROGRESS || || Get repeatable deployment story || yellow || 2012-03-07 || IN-PROGRESS || || Determine scaling behavior || yellow || 2012-03-07 || || || Root out instability || yellow || 2012-03-21 || || || Secure production hardware || flacoste || 2012-03-07 || || |
|| Secure test hardware || flacoste || 2012-02-28 || COMPLETED || || Get repeatable deployment story || yellow || 2012-03-07 || COMPLETED || || Determine scaling behavior || yellow || 2012-03-13 (2012-03-07) || IN-PROGRESS|| || Root out instability || yellow || 2012-03-21 || IN-PROGRESS || || Secure production hardware || flacoste || 2012-03-21 (2012-03-07) || || |
Line 46: | Line 46: |
* [yellow] buildbot charms in the official repo * [yellow] Have the LP build steps tested and working within the buildbot environment |
|
Line 49: | Line 47: |
* [yellow] Have a deployment plan | * [yellow] Bug fixes for test failures discovered in parallel test runs |
Parallel Testing
See also paralleltest bug tag
Squad started: 2012-01-02
Current week: 8
Next checkpoint: 2012-03-21
Scope
Out of scope
As documented in the LEP.
Blockers
None
Deliverables
Whatever you need to keep track of deliverables. An example, including some common ones is included below. Deliverables often correspond to a group of user stories or a single user story
Item |
Owner |
Expected date |
Status |
Signed off LEPs |
lifeless |
2012-01-05 |
COMPLETED |
Secure test hardware |
flacoste |
2012-02-28 |
COMPLETED |
Get repeatable deployment story |
yellow |
2012-03-07 |
COMPLETED |
Determine scaling behavior |
yellow |
2012-03-13 (2012-03-07) |
IN-PROGRESS |
Root out instability |
yellow |
2012-03-21 |
IN-PROGRESS |
Secure production hardware |
flacoste |
2012-03-21 (2012-03-07) |
|
Feature documentation |
gary |
|
|
Blog post |
gary |
|
|
Notes
Checkpoints Notes
Action items for next checkpoint
- [yellow] Scaling assessment based on experimental results
- [yellow] Bug fixes for test failures discovered in parallel test runs