Size: 1673
Comment: Bi-weekly checkpoints
|
← Revision 8 as of 2012-04-12 00:47:39 ⇥
Size: 1766
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 6: | Line 6: |
'''Current week:''' 8<<BR>> '''Next [[PolicyandProcess/FeatureDevelopmentCheckpoint|checkpoint]]:''' 2012-03-21 |
'''Current week:''' 14<<BR>> '''Next [[PolicyandProcess/FeatureDevelopmentCheckpoint|checkpoint]]:''' 2012-04-18 |
Line 29: | Line 29: |
|| Determine scaling behavior || yellow || 2012-03-13 (2012-03-07) || IN-PROGRESS|| | || Determine scaling behavior || yellow || 2012-03-27 (2012-03-07) || IN-PROGRESS|| |
Line 31: | Line 31: |
|| Secure production hardware || flacoste || 2012-03-21 (2012-03-07) || || | || Secure production hardware || flacoste || 2012-04-04 (2012-03-07) || || |
Line 46: | Line 46: |
* [yellow] Bug fixes for test failures discovered in parallel test runs. | |
Line 47: | Line 48: |
* [yellow] Bug fixes for test failures discovered in parallel test runs | * [yellow] Get data center box running tests, and have a single comparison run with ec2. |
Parallel Testing
See also paralleltest bug tag
Squad started: 2012-01-02
Current week: 14
Next checkpoint: 2012-04-18
Scope
Out of scope
As documented in the LEP.
Blockers
None
Deliverables
Whatever you need to keep track of deliverables. An example, including some common ones is included below. Deliverables often correspond to a group of user stories or a single user story
Item |
Owner |
Expected date |
Status |
Signed off LEPs |
lifeless |
2012-01-05 |
COMPLETED |
Secure test hardware |
flacoste |
2012-02-28 |
COMPLETED |
Get repeatable deployment story |
yellow |
2012-03-07 |
COMPLETED |
Determine scaling behavior |
yellow |
2012-03-27 (2012-03-07) |
IN-PROGRESS |
Root out instability |
yellow |
2012-03-21 |
IN-PROGRESS |
Secure production hardware |
flacoste |
2012-04-04 (2012-03-07) |
|
Feature documentation |
gary |
|
|
Blog post |
gary |
|
|
Notes
Checkpoints Notes
Action items for next checkpoint
- [yellow] Bug fixes for test failures discovered in parallel test runs.
- [yellow] Scaling assessment based on experimental results
- [yellow] Get data center box running tests, and have a single comparison run with ec2.