Parallel Testing
See also paralleltest bug tag
Squad started: 2012-01-02
Current week: 6
Next checkpoint: 2012-02-22
Scope
Out of scope
As documented in the LEP.
Blockers
None
Deliverables
Whatever you need to keep track of deliverables. An example, including some common ones is included below. Deliverables often correspond to a group of user stories or a single user story
Item |
Owner |
Expected date |
Status |
Signed off LEPs |
lifeless |
2012-01-05 |
COMPLETED |
Secure test hardware |
flacoste |
2012-02-28 |
IN-PROGRESS |
Get repeatable deployment story |
yellow |
2012-03-07 |
IN-PROGRESS |
Determine scaling behavior |
yellow |
2012-03-07 |
|
Root out instability |
yellow |
2012-03-21 |
|
Secure production hardware |
flacoste |
2012-03-07 |
|
Feature documentation |
gary |
|
|
Blog post |
gary |
|
|
Notes
Checkpoints Notes
Action items for next checkpoint
- [yellow] buildbot charms in the official repo
- [yellow] Have the LP build steps tested and working within the buildbot environment
- [yellow] Scaling assessment based on experimental results
- [yellow] Have a deployment plan